SUNSHINE BUILD LOG
Date Activity
10/8/2006 Build Transom and Stem
10/13/2006 Butt-Join Side 1/4" Plywood - Templates for Frames 1-3
10/14/2006 Constructed Frames - Marked and Cut Sides
10/15/2006 Connected Stem and Transom to Frames - Built Frame 4
10/16/2006 Cut Stem - Planned Bottom of Side plywood
10/20/2006 Butt-Join Bottom 3/8" Plywood
10/21/2006 Mark Bottom & install & patch & sand hull
10/22/2006 Fiberglass tape edges & first coat epoxy outside
10/23/2006 Sand outslide patch & second coat epoxy
10/24/2006 sand new glass - 3rd coat of epoxy
10/27/2006 Install Oak gunnels epoxy and screw
10/28/2006 Build Mast Seat and Mast Step - Install
10/29/2006 Build Dagger Board Box - Install
10/30/2006 Cut & install Center Seat and connect to Dagger Board Box
10/31/2006 Cut Daggerboard braces - Installed - epoxy filet in Stem
11/3/2006 Trimmed Gunnel, Patched gunnel sides - Cut & Installed Center Front Seat - Prep for inside tape
11/4/2006 Fiberglass tape inside hull
11/15/2006 Cut and installed back seat frame
11/16/2006 Side seat frames & partition on back seat
11/17/2006 Plug holes in side, Cut & install side vertical - glass inside back seat
11/18/2006 Filet daggerboard box Install front of side seats
11/19/2006 Sand interior - epoxy inside flotation chambers
11/25/2006 Cut & Fit Front and Rear Seats - Cut & Install Interior Stem and Breasthook
11/30/2006 Install bracing for side seats
12/1/2006 Cut top side seats and trimmed - installed first layer of foam
12/2/2006 Installed remaining foam - trimmed - installed side and front seats and patched
12/3/2006 Epoxy and taped side and front seats
12/7/2006 Installed oar locks and glass-epoxy area inside around locks - planned daggerboard
12/16/2006 Sanded Daggerboard box - epoxyed daggerboard
12/31/2006 Sanded outside and inside - cut and installed skeg and shaffing strips, patched outside hull
1/1/2007 Sand and expoy outside hull
1/3/2007 Drew Rudder
1/5/2007 Cut rudder - glassed one side
1/6/2007 Sanded interior patched daggerboard box (inside), glassed 2nd side of rudder
1/8/2007 Epoxy Inside - Final coat
1/10/2007 Cut tiller, coat underside of exposed seats/maststep
1/11/2007 Installed rudder hardware and epoxy coat
1/13/2007 Attached tiller to rudder/ laminated top spar
1/15/2007 Attached Rudder - repaired tiller angle - liaminated bottom spars
1/18/2007 Cut goosneck laminate - epoxy glass other side of tiller fix.
1/19/2007 Planned lower spar, attached gooseneck and epoxyed
1/20/2007 Mast top pulley installation, planned upper spar.
1/21/2007 Test sail - trim spars - install fairleads, epoxy patch spars - mast, and rudder
1/30/2007 Final epoxy of mast
2/1/2007 Sand (enlarge) dagger box & epoxy - sand dagger board
2/3/2007 Sand & final epoxy of dagger board
2/11/2007 Install dagger board tops - epoxy & install spart cleats
2/18/2007 Prime hull & paint hull
2/19/2007 2nd coat of paint
2/24/2007 Final scrub of interior
2/25/2007 Full rig up testing, photos for licenseing
3/7/2007 glass & epoxy rear seat
3/9/2007 Name and Registration
3/10/2007 Launch!!